A draft structure for a risk trackingsheet has been provided below: 1.Risk identifier 2.Risk status 3.Risk description 4.Mitigation steps 5.Mitigation status Which of the following should be ADDED…

The correct answer is A. Risk rating. See the full explanation below for the reasoning.

Question

A draft structure for a risk trackingsheet has been provided below:

1.Risk identifier 2.Risk status 3.Risk description 4.Mitigation steps 5.Mitigation status Which of the following should be ADDED to the risk tracking sheet?

Options

  • ARisk rating
  • BStakeholder risk tolerance
  • CRevised project schedule
  • DRisk matrix

How the community answered

(58 responses)
  • A
    78% (45)
  • B
    7% (4)
  • C
    12% (7)
  • D
    3% (2)

Community Discussion