Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?

The correct answer is C. CPM. See the full explanation below for the reasoning.

Question

Which of the following scheduling algorithms establishes floats, durations, and paths between work schedule activities?

Options

  • AAON
  • BPERT
  • CCPM
  • DGERT

How the community answered

(31 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    84% (26)
  • D
    6% (2)