JK0-017 · Question #341

During the course of a project, key stakeholders have requested new requirements after the business requirements document has already been signed off. Which of the following should have been…

The correct answer is D. Agree on a process to deal with project change requests. See the full explanation below for the reasoning.

Question

During the course of a project, key stakeholders have requested new requirements after the business requirements document has already been signed off. Which of the following should have been performed earlier in the project in order to deal with this situation?

Options

  • AEnsure that stakeholders understand that once requirements are approved the scope cannot be
  • BDevelop a clear communications flow between the project and business stakeholders.
  • CPerform multiple rounds of requirements solicitation before permanently locking down the scope.
  • DAgree on a process to deal with project change requests.

How the community answered

(17 responses)
  • A
    6% (1)
  • C
    12% (2)
  • D
    82% (14)

Community Discussion

No community discussion yet for this question.