Which of the following should be used when determining the details of a project component or scope entry?

The correct answer is A. WBS Dictionary. See the full explanation below for the reasoning.

Question

Which of the following should be used when determining the details of a project component or scope entry?

Options

  • AWBS Dictionary
  • BProject Management Plan
  • CWork Breakdown Structure
  • DProject Charter

How the community answered