A project's deliverable has been assigned to a team located in a different country. Although it is understood that daily reports are due by close of business every weekday, the external team's…
The correct answer is C. The project manager has not taken into consideration the time zone difference. See the full explanation below for the reasoning.
Question
A project's deliverable has been assigned to a team located in a different country. Although it is understood that daily reports are due by close of business every weekday, the external team's reports are consistently being delivered after business hours. Which of the following is MOST likely occurring?
Options
- AThe external project team did not understand the report requirements due to the language barrier.
- BExternal project team members are always allowed to deliver reports late.
- CThe project manager has not taken into consideration the time zone difference.
- DCultural differences between the project manager and the external team were not considered.
How the community answered
(32 responses)- A3% (1)
- B13% (4)
- C81% (26)
- D3% (1)