JK0-017 · Question #338

Some of the stakeholders are losing interest in the project because of its length. Which of the following should the project manager implement in this situation?

The correct answer is C. Implement a concise and reoccurring communication plan which focuses on the project goal and. See the full explanation below for the reasoning.

Question

Some of the stakeholders are losing interest in the project because of its length. Which of the following should the project manager implement in this situation?

Options

  • ARemove the stakeholders who are losing interest to ensure successful completion of the project.
  • BLimit communication with the stakeholders to the bare minimum and only report on the progress
  • CImplement a concise and reoccurring communication plan which focuses on the project goal and
  • DReview the project goal with the stakeholder and allow them to make the appropriate changes to

How the community answered

(29 responses)
  • A
    17% (5)
  • B
    3% (1)
  • C
    72% (21)
  • D
    7% (2)