JK0-017 · Question #337

The project manager wants to report to the stakeholders to date project's cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, which of the following…

The correct answer is C. -$10,000. See the full explanation below for the reasoning.

Question

The project manager wants to report to the stakeholders to date project's cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, which of the following is the cost variance?

Options

  • A-5%
  • B5%
  • C-$10,000
  • D$10,000

How the community answered

(53 responses)
  • A
    6% (3)
  • B
    13% (7)
  • C
    77% (41)
  • D
    4% (2)