CompTIA
JK0-017 · Question #337
The project manager wants to report to the stakeholders to date project's cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, which of the following…
The correct answer is C. -$10,000. See the full explanation below for the reasoning.
Question
The project manager wants to report to the stakeholders to date project's cost performance. If the total of completed work to date is $200,000 and the actual cost is $210,000, which of the following is the cost variance?
Options
- A-5%
- B5%
- C-$10,000
- D$10,000
How the community answered
(53 responses)- A6% (3)
- B13% (7)
- C77% (41)
- D4% (2)
Community Discussion
No community discussion yet for this question.