The project manager is reviewing the Pareto chart to identify if the life cycle of a deliverable is producing software bugs. Which of the following are represented in the chart? (Select TWO).
The correct answer is B. Percentage of bug types occurring C. Software bug counts. See the full explanation below for the reasoning.
Question
The project manager is reviewing the Pareto chart to identify if the life cycle of a deliverable is producing software bugs. Which of the following are represented in the chart? (Select TWO).
Options
- ANumber of work units affected by the bug
- BPercentage of bug types occurring
- CSoftware bug counts
- DRoot cause of bug occurrence
- EAffect of the bug occurrence
How the community answered
(29 responses)- A3% (1)
- B72% (21)
- D14% (4)
- E10% (3)