Which of the following is the project manager implementing when they allocate additional resources to a set of tasks that are in the critical path and are slowing down the project completion?
The correct answer is A. Crashing. See the full explanation below for the reasoning.
Question
Which of the following is the project manager implementing when they allocate additional resources to a set of tasks that are in the critical path and are slowing down the project completion?
Options
- ACrashing
- BOptimizing
- CControlling
- DFast tracking
How the community answered
(33 responses)- A70% (23)
- B18% (6)
- C9% (3)
- D3% (1)