CompTIA
JK0-017 · Question #334
Additional company employees have been assigned to the project. Which of the following will be affected?
The correct answer is A. The timeline may be positively affected at the expense of the project cost. See the full explanation below for the reasoning.
Question
Additional company employees have been assigned to the project. Which of the following will be affected?
Options
- AThe timeline may be positively affected at the expense of the project cost.
- BThis change does not affect the triple constraint because the additional employees are already on
- CThe quality of the product will improve but it will add more time to the project to train the new
- DTotal project cost will be reduced because the project can now be completed sooner.
How the community answered
(14 responses)- A79% (11)
- B14% (2)
- C7% (1)
Community Discussion
No community discussion yet for this question.