JK0-017 · Question #333
A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed. Which of the following should be done…
The correct answer is D. Perform an impact analysis. See the full explanation below for the reasoning.
Question
A project team member has identified a required change to one of their assigned tasks. The change would alter the order in which other tasks must be completed. Which of the following should be done NEXT?
Options
- AImplement the change
- BUpdate the change registry
- CDocument the change
- DPerform an impact analysis
How the community answered
(19 responses)- A5% (1)
- C11% (2)
- D84% (16)