JK0-017 · Question #332
While performing a scheduled walkthrough at a construction site, the customer points out a discrepancy. Which of the following is the FIRST step that should be taken before submitting a change…
The correct answer is B. Identify the change. See the full explanation below for the reasoning.
Question
While performing a scheduled walkthrough at a construction site, the customer points out a discrepancy. Which of the following is the FIRST step that should be taken before submitting a change control form?
Options
- AConsult the project sponsor
- BIdentify the change
- CPerform a feasibility study
- DPerform impact analysis
How the community answered
(18 responses)- A6% (1)
- B83% (15)
- D11% (2)