A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the following is TRUE…
The correct answer is D. Project schedule may be affected and the project manager must follow the change control. See the full explanation below for the reasoning.
Question
A new software solution is being deployed. The customer realizes that an important piece of the software must be purchased in order for the project to be successful. Which of the following is TRUE about this scenario?
Options
- AThe new piece of software will most likely expand the scope of the project therefore a new scope
- BThe current project must be completed and a new project can be started to implement the
- CQuality management metrics are affected therefore the project manager should review the quality
- DProject schedule may be affected and the project manager must follow the change control
How the community answered
(35 responses)- A11% (4)
- B3% (1)
- C6% (2)
- D80% (28)