After the ground breaking at a new construction site, the pile driving operation comes to a full stop due to the nature of the terrain. Which of the following is MOST likely to occur?

The correct answer is B. The project manager must manage the new issue as the project schedule could be delayed. See the full explanation below for the reasoning.

Question

After the ground breaking at a new construction site, the pile driving operation comes to a full stop due to the nature of the terrain. Which of the following is MOST likely to occur?

Options

  • AThe project communication plan must be updated and a stakeholder meeting must be scheduled.
  • BThe project manager must manage the new issue as the project schedule could be delayed.
  • CThe project manager must implement conflict resolution and review the resource requirement.
  • DThe project scope statement must be reviewed and the project manager must prepare a

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    86% (42)
  • C
    8% (4)
  • D
    4% (2)