Which of the following is BEST suited for assigning resources to WBS tasks?

The correct answer is D. WBS defines activities and deliverables that can be mapped to functional teams. See the full explanation below for the reasoning.

Question

Which of the following is BEST suited for assigning resources to WBS tasks?

Options

  • AWBS defines functional teams which should then be mapped to project scope items
  • BWBS contains the project schedule which should be used to determine timing of when to engage
  • CWBS defines the description of the end result delivered by the project
  • DWBS defines activities and deliverables that can be mapped to functional teams

How the community answered

(60 responses)
  • A
    8% (5)
  • B
    12% (7)
  • C
    3% (2)
  • D
    77% (46)