Which of the following is the MAIN difference between bottom up and top down cost estimation?
The correct answer is A. Bottom up leads to a more accurate cost estimate than top down because it is performed by. See the full explanation below for the reasoning.
Question
Which of the following is the MAIN difference between bottom up and top down cost estimation?
Options
- ABottom up leads to a more accurate cost estimate than top down because it is performed by
- BTop down leads to a more accurate cost estimate because it is performed by upper management
- CBottom up leads to a less accurate cost estimate because it is breaks down the task into smaller
- DBoth top down and bottom up are equally accurate estimation of a project's total cost because
How the community answered
(56 responses)- A73% (41)
- B4% (2)
- C18% (10)
- D5% (3)
Community Discussion