Question

Which of the following is the MAIN difference between bottom up and top down cost estimation?

Options

  • ABottom up leads to a more accurate cost estimate than top down because it is performed by
  • BTop down leads to a more accurate cost estimate because it is performed by upper management
  • CBottom up leads to a less accurate cost estimate because it is breaks down the task into smaller
  • DBoth top down and bottom up are equally accurate estimation of a project's total cost because