The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the following is BEST suited…
The correct answer is B. ADM. See the full explanation below for the reasoning.
Question
The project manager is sequencing a set of activities. They discover that some of the activities may or may not occur based on the outcome of other activities. Which of the following is BEST suited in this situation to show the activities' logical relationship?
Options
- AGantt
- BADM
- CCCB
- DCCM
How the community answered
(25 responses)- A12% (3)
- B80% (20)
- C4% (1)
- D4% (1)