JK0-017 · Question #325
A project manager is entering the list of a project's activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to end. Which of the…
The correct answer is A. Gantt chart. See the full explanation below for the reasoning.
Question
A project manager is entering the list of a project's activities with their estimated begin and end time to visualize which activities overlap and when the project is scheduled to end. Which of the following is the project manager building?
Options
- AGantt chart
- BWork Breakdown Structure
- CCritical Path
- DPERT chart
How the community answered
(27 responses)- A81% (22)
- C7% (2)
- D11% (3)