JK0-017 · Question #328
Which of the following purchasing processes should a project team use to ensure that the work will be done per company specifications, while selecting the overall cheapest provider?
The correct answer is B. RFP. See the full explanation below for the reasoning.
Question
Which of the following purchasing processes should a project team use to ensure that the work will be done per company specifications, while selecting the overall cheapest provider?
Options
- ARFI
- BRFP
- CRFC
- DRFQ
How the community answered
(32 responses)- A3% (1)
- B81% (26)
- C3% (1)
- D13% (4)