A statement of work (SOW) has been heavily revised by the stakeholders. Which of the following should be implemented to make it easier to determine how many times the document has been revised?
The correct answer is A. Version control. See the full explanation below for the reasoning.
Question
A statement of work (SOW) has been heavily revised by the stakeholders. Which of the following should be implemented to make it easier to determine how many times the document has been revised?
Options
- AVersion control
- BA document revision date
- CApproval signatures from each stakeholder
- DA change request
How the community answered
(34 responses)- A82% (28)
- B6% (2)
- C3% (1)
- D9% (3)