After a change control board meeting, which of the following actions should the project manager do NEXT?

The correct answer is A. Notify the requester of the verdict. See the full explanation below for the reasoning.

Question

After a change control board meeting, which of the following actions should the project manager do NEXT?

Options

  • ANotify the requester of the verdict.
  • BReview the impact of proposed change.
  • CUpdate the project scope statement.
  • DDocument the specific change request.

How the community answered

(23 responses)
  • A
    78% (18)
  • B
    13% (3)
  • C
    4% (1)
  • D
    4% (1)