Which of the following is the BEST method to avoid staffing conflict between resource managers and project managers?

The correct answer is D. Formally request team members early. See the full explanation below for the reasoning.

Question

Which of the following is the BEST method to avoid staffing conflict between resource managers and project managers?

Options

  • AAllow team members to enter the project as best fits their schedule.
  • BAsk the project sponsor for team member assignments.
  • CClaim the best department resources before the project starts.
  • DFormally request team members early.

How the community answered

(24 responses)
  • A
    4% (1)
  • B
    8% (2)
  • C
    4% (1)
  • D
    83% (20)