CompTIA
JK0-017 · Question #312
Which of the following human resource outputs would a project manager use to determine a team member's skills?
The correct answer is C. Competency. See the full explanation below for the reasoning.
Question
Which of the following human resource outputs would a project manager use to determine a team member's skills?
Options
- ARole
- BAccountability
- CCompetency
- DResponsibility
How the community answered
(60 responses)- A5% (3)
- B10% (6)
- C70% (42)
- D15% (9)
Community Discussion