A project manager of a particular project receives formal notification that a vendor has gone out of business. New vendors with similar products at similar costs have been identified. Which of the…
The correct answer is A. Initiate RFQs to qualified vendors, update the project management plan and communicate the. See the full explanation below for the reasoning.
Question
A project manager of a particular project receives formal notification that a vendor has gone out of business. New vendors with similar products at similar costs have been identified. Which of the following should the project manager do FIRST?
Options
- AInitiate RFQs to qualified vendors, update the project management plan and communicate the
- BUndertake a make-or-buy decision analysis; communicate the issue with the project sponsor
- CCall a stakeholder meeting following the project communications plan to urgently review the
- DCommunicate the issue with the project sponsor following the project communications plan, call a
How the community answered
(30 responses)- A83% (25)
- B10% (3)
- C3% (1)
- D3% (1)