In a Gantt chart, how are milestones displayed?

The correct answer is A. An activity with zero day duration. See the full explanation below for the reasoning.

Question

In a Gantt chart, how are milestones displayed?

Options

  • AAn activity with zero day duration
  • BAn activity with one day duration
  • CActivity-on-node with a finish-to-finish precedence
  • DEnd-to-end bar graph showing the time to complete a task

How the community answered

(41 responses)
  • A
    73% (30)
  • B
    15% (6)
  • C
    10% (4)
  • D
    2% (1)