JK0-017 · Question #300
In a Gantt chart, how are milestones displayed?
The correct answer is A. An activity with zero day duration. See the full explanation below for the reasoning.
Question
In a Gantt chart, how are milestones displayed?
Options
- AAn activity with zero day duration
- BAn activity with one day duration
- CActivity-on-node with a finish-to-finish precedence
- DEnd-to-end bar graph showing the time to complete a task
How the community answered
(41 responses)- A73% (30)
- B15% (6)
- C10% (4)
- D2% (1)