An analysis of the cost-benefit trade-offs for a project should be included as part of the:
The correct answer is D. Quality plan. See the full explanation below for the reasoning.
Question
An analysis of the cost-benefit trade-offs for a project should be included as part of the:
Options
- AWork plan
- BRisk register
- CProject charter
- DQuality plan
How the community answered
(36 responses)- A3% (1)
- B11% (4)
- C6% (2)
- D81% (29)