During the execution phase of a large scale project, a new stakeholder is identified that has vital information that could impact the completion of the project. Which of the following is the FIRST…
The correct answer is A. Call a meeting of the key stakeholders to introduce the new stakeholder and discuss the new. See the full explanation below for the reasoning.
Question
During the execution phase of a large scale project, a new stakeholder is identified that has vital information that could impact the completion of the project. Which of the following is the FIRST activity the project manager should undertake?
Options
- ACall a meeting of the key stakeholders to introduce the new stakeholder and discuss the new
- BHalt the project immediately; accept any changes requested by the new stakeholder once all
- CDiscuss the new stakeholder's inputs/requirements with the project sponsor and take advice on
- DRequest that the new stakeholder raise an urgent change request for authorization to change the
How the community answered
(38 responses)- A79% (30)
- B11% (4)
- C3% (1)
- D8% (3)
Community Discussion
No community discussion yet for this question.