During the execution phase of a large scale project, a new stakeholder is identified that has vital information that could impact the completion of the project. Which of the following is the FIRST…

The correct answer is A. Call a meeting of the key stakeholders to introduce the new stakeholder and discuss the new. See the full explanation below for the reasoning.

Question

During the execution phase of a large scale project, a new stakeholder is identified that has vital information that could impact the completion of the project. Which of the following is the FIRST activity the project manager should undertake?

Options

  • ACall a meeting of the key stakeholders to introduce the new stakeholder and discuss the new
  • BHalt the project immediately; accept any changes requested by the new stakeholder once all
  • CDiscuss the new stakeholder's inputs/requirements with the project sponsor and take advice on
  • DRequest that the new stakeholder raise an urgent change request for authorization to change the

How the community answered

(38 responses)
  • A
    79% (30)
  • B
    11% (4)
  • C
    3% (1)
  • D
    8% (3)