Question

A WBS dictionary:

Options

  • Ais a granular hierarchical breakdown of the work to be undertaken by the project team, to meet
  • Bprovides a description of all of the components of a WBS, and a brief summary of its SOW, scope
  • Callocates the WBS components to appropriate teams or named individuals within teams.
  • Ddescribes how a project will be decomposed into smaller, manageable subprojects or work

Unlock JK0-017 to see the answer