In which of the following project organizations would the project management be handled by a marketing manager?

The correct answer is D. Functional. See the full explanation below for the reasoning.

Question

In which of the following project organizations would the project management be handled by a marketing manager?

Options

  • AMatrix
  • BBalanced
  • CProjectized
  • DFunctional

How the community answered

(40 responses)
  • A
    5% (2)
  • B
    13% (5)
  • C
    8% (3)
  • D
    75% (30)