Which of the following may have a significant adverse impact upon the successful completion of an international project? (Select THREE).
The correct answer is A. Time zones B. Travel costs F. Language barriers. See the full explanation below for the reasoning.
Question
Which of the following may have a significant adverse impact upon the successful completion of an international project? (Select THREE).
Options
- ATime zones
- BTravel costs
- CCo-location of resources
- DThe project plan
- EScheduled vacations
- FLanguage barriers
How the community answered
(25 responses)- A72% (18)
- C8% (2)
- D16% (4)
- E4% (1)