JK0-017 · Question #290
A project scope document should include which of the following items? (Select TWO).
The correct answer is C. Key performance indicators D. Detailed objectives. See the full explanation below for the reasoning.
Question
A project scope document should include which of the following items? (Select TWO).
Options
- ACost control
- BContinuous service improvements
- CKey performance indicators
- DDetailed objectives
- ERisk management plan
How the community answered
(44 responses)- A7% (3)
- B16% (7)
- C73% (32)
- E5% (2)
Community Discussion
No community discussion yet for this question.