There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:
The correct answer is A. Accept it. See the full explanation below for the reasoning.
Question
There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:
Options
- AAccept it
- BAvoid it
- CMinimize it
- DMitigate it
How the community answered
(41 responses)- A76% (31)
- B15% (6)
- C2% (1)
- D7% (3)