There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:

The correct answer is A. Accept it. See the full explanation below for the reasoning.

Question

There is a high probability of a needed resource becoming unavailable. The project manager determines the impact to be low; therefore, the MOST likely response to the identified risk is to:

Options

  • AAccept it
  • BAvoid it
  • CMinimize it
  • DMitigate it

How the community answered

(41 responses)
  • A
    76% (31)
  • B
    15% (6)
  • C
    2% (1)
  • D
    7% (3)