Which of the following would be included in the project transition plan?
The correct answer is C. Maintenance responsibilities of the project deliverables. See the full explanation below for the reasoning.
Question
Which of the following would be included in the project transition plan?
Options
- ASpecifications used for quality control measurements.
- BComparison of project deliverables with organizational strategic goals.
- CMaintenance responsibilities of the project deliverables.
- DAnalysis of the project expenditures.
How the community answered
(57 responses)- A4% (2)
- B4% (2)
- C82% (47)
- D11% (6)