Question

Which of the following would be included in the project transition plan?

Options

  • ASpecifications used for quality control measurements.
  • BComparison of project deliverables with organizational strategic goals.
  • CMaintenance responsibilities of the project deliverables.
  • DAnalysis of the project expenditures.