During which of the following process groups is the project charter developed?

The correct answer is A. Pre-project setup. See the full explanation below for the reasoning.

Question

During which of the following process groups is the project charter developed?

Options

  • APre-project setup
  • BProject execution
  • CProject planning
  • DProject control

How the community answered

(36 responses)
  • A
    72% (26)
  • B
    6% (2)
  • C
    6% (2)
  • D
    17% (6)

Community Discussion