CompTIA
JK0-017 · Question #280
A project manager needs to determine how much it will cost for a third party to complete certain deliverables and the steps they will take to complete those deliverables. Which of the following…
The correct answer is B. Issue an RFP. See the full explanation below for the reasoning.
Question
A project manager needs to determine how much it will cost for a third party to complete certain deliverables and the steps they will take to complete those deliverables. Which of the following should the project manager do to gather this information?
Options
- AIssue an RFQ
- BIssue an RFP
- CCreate a WBS
- DDevelop a SOW
How the community answered
(21 responses)- A5% (1)
- B71% (15)
- C5% (1)
- D19% (4)
Community Discussion
No community discussion yet for this question.