The key stakeholder requires the project manager to advance the completion date before funding runs out. The project manager has had problems with this stakeholder in the past and wants to document…
The correct answer is A. Complete a project change request form. B. Analyze the project impact. See the full explanation below for the reasoning.
Question
The key stakeholder requires the project manager to advance the completion date before funding runs out. The project manager has had problems with this stakeholder in the past and wants to document this request. Which of the following should the project manager do? (Select TWO).
Options
- AComplete a project change request form.
- BAnalyze the project impact.
- CUpdate the project scope statement.
- DRevise the scope management plan.
- EMonitor the work performance.
How the community answered
(48 responses)- A73% (35)
- C15% (7)
- D8% (4)
- E4% (2)