A team member has approached the project manager for an update on the project status and next tasks. Which of the following should the project manager do NEXT?
The correct answer is C. Review the communications plan to determine why they were unaware. See the full explanation below for the reasoning.
Question
A team member has approached the project manager for an update on the project status and next tasks. Which of the following should the project manager do NEXT?
Options
- ASpeak with the team member's manager about their performance
- BResend the latest status report and project plan to the team member
- CReview the communications plan to determine why they were unaware
- DSend the communications plan to the team member
How the community answered
(59 responses)- A8% (5)
- B5% (3)
- C85% (50)
- D2% (1)