Question
A new team has been put together for a construction project. The project currently does not have a cost estimate but the company has done other builds similar to the one at task and needs the estimate at the end of the week. Which of the following approaches would be BEST to determine the cost?
Options
- AAnalogous
- BBottom up
- CTop down
- DExpert judgment
How the community answered
(19 responses)- A68% (13)
- B5% (1)
- C16% (3)
- D11% (2)