CompTIA
JK0-017 · Question #260
A project manager has been assigned to a software development solution at the ABC Inc. Which of the following should the sponsor expect within the scope document? (Select THREE).
The correct answer is C. Objectives F. Project exclusions H. Constraints. See the full explanation below for the reasoning.
Question
A project manager has been assigned to a software development solution at the ABC Inc. Which of the following should the sponsor expect within the scope document? (Select THREE).
Options
- ARisk register template
- BMilestones
- CObjectives
- DIssue log template
- EResource requirements
- FProject exclusions
- GCommunication expectations
- HConstraints
How the community answered
(49 responses)- A4% (2)
- B2% (1)
- C73% (36)
- E12% (6)
- G8% (4)
Community Discussion
No community discussion yet for this question.