Which of the following shows the interdependencies between activities on a project schedule?
The correct answer is C. Network diagram. See the full explanation below for the reasoning.
Question
Which of the following shows the interdependencies between activities on a project schedule?
Options
- AMilestone chart
- BPareto diagram
- CNetwork diagram
- DScatter diagram
How the community answered
(28 responses)- A14% (4)
- B4% (1)
- C79% (22)
- D4% (1)