The project team determined that using a multipoint estimate is more appropriate than single point estimate. Which of the following network diagram methods would be MOST appropriate?
The correct answer is C. PERT. See the full explanation below for the reasoning.
Question
The project team determined that using a multipoint estimate is more appropriate than single point estimate. Which of the following network diagram methods would be MOST appropriate?
Options
- AGERT
- BCritical chain
- CPERT
- DCritical path
How the community answered
(45 responses)- A4% (2)
- B11% (5)
- C82% (37)
- D2% (1)