JK0-017 · Question #233

Stakeholders have submitted change requests via email, telephone calls, stopping by, during meetings, and using the change request form. Also, once the change request is made, the stakeholders…

The correct answer is C. Process flow diagram. See the full explanation below for the reasoning.

Question

Stakeholders have submitted change requests via email, telephone calls, stopping by, during meetings, and using the change request form. Also, once the change request is made, the stakeholders expect the request to be immediately acted upon. Which of the following can be produced to aid in the stakeholders' understanding of how change control is performed on the project?

Options

  • AIssue log
  • BStakeholder register
  • CProcess flow diagram
  • DWork breakdown structure

How the community answered

(65 responses)
  • A
    14% (9)
  • B
    8% (5)
  • C
    75% (49)
  • D
    3% (2)