A project manager needs to assign team members to begin project work. Which of the following items must the project manager have before assignments can be made? (Select TWO).
The correct answer is B. Resource Availability C. Work Breakdown Structure (WBS). See the full explanation below for the reasoning.
Question
A project manager needs to assign team members to begin project work. Which of the following items must the project manager have before assignments can be made? (Select TWO).
Options
- AQuality Management Plan
- BResource Availability
- CWork Breakdown Structure (WBS)
- DFeasibility Analysis
- ERisk Management Plan
How the community answered
(33 responses)- A12% (4)
- B76% (25)
- D3% (1)
- E9% (3)