Which of the following is the FINAL step in pre-project setup?

The correct answer is B. Sign the approval document. See the full explanation below for the reasoning.

Question

Which of the following is the FINAL step in pre-project setup?

Options

  • AComplete the work breakdown structure (WBS).
  • BSign the approval document.
  • CCreate the needed stakeholder forms.
  • DValidate the project.

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    77% (20)
  • C
    4% (1)
  • D
    12% (3)