JK0-017 · Question #20

Using the work breakdown structure (WBS) and knowledge of team member availability, the project manager is able to:

The correct answer is D. assign resources to scheduled tasks. See the full explanation below for the reasoning.

Question

Using the work breakdown structure (WBS) and knowledge of team member availability, the project manager is able to:

Options

  • Ahold the project kick-off meeting.
  • Bcreate the communication plan.
  • Ccreate the cost management plan.
  • Dassign resources to scheduled tasks.

How the community answered

(20 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    10% (2)
  • D
    80% (16)

Community Discussion

No community discussion yet for this question.

Full JK0-017 Practice