CompTIA
JK0-017 · Question #199
A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:
The correct answer is A. Arisk register. See the full explanation below for the reasoning.
Question
A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:
Options
- AArisk register.
- BChange management.
- CAn issues log.
- DAcommunication plan.
How the community answered
(44 responses)- A70% (31)
- B5% (2)
- C16% (7)
- D9% (4)
Community Discussion