JK0-017 · Question #199

A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:

The correct answer is A. Arisk register. See the full explanation below for the reasoning.

Question

A project is having issues because uncertain events have occurred that were not tracked and planned for. This could have been avoided by using:

Options

  • AArisk register.
  • BChange management.
  • CAn issues log.
  • DAcommunication plan.

How the community answered

(44 responses)
  • A
    70% (31)
  • B
    5% (2)
  • C
    16% (7)
  • D
    9% (4)