A project is having issues because people are making modifications to the servers without manager approval. This could have been avoided by using:
The correct answer is A. Change management. See the full explanation below for the reasoning.
Question
A project is having issues because people are making modifications to the servers without manager approval. This could have been avoided by using:
Options
- AChange management.
- BAn issues log.
- CAcommunication plan.
- DArisk register.
How the community answered
(35 responses)- A74% (26)
- B6% (2)
- C3% (1)
- D17% (6)