A project is having issues because the team is unclear what they should be doing and who should be doing it. This could have been avoided by using:

The correct answer is C. Acommunication plan. See the full explanation below for the reasoning.

Question

A project is having issues because the team is unclear what they should be doing and who should be doing it. This could have been avoided by using:

Options

  • AArisk register.
  • BChange management.
  • CAcommunication plan.
  • DAn issues log.

How the community answered

(51 responses)
  • A
    4% (2)
  • B
    8% (4)
  • C
    73% (37)
  • D
    16% (8)