A project is having issues because the team is unclear what they should be doing and who should be doing it. This could have been avoided by using:
The correct answer is C. Acommunication plan. See the full explanation below for the reasoning.
Question
A project is having issues because the team is unclear what they should be doing and who should be doing it. This could have been avoided by using:
Options
- AArisk register.
- BChange management.
- CAcommunication plan.
- DAn issues log.
How the community answered
(51 responses)- A4% (2)
- B8% (4)
- C73% (37)
- D16% (8)