CompTIA
JK0-017 · Question #196
The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having…
The correct answer is C. Sharing. See the full explanation below for the reasoning.
Question
The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies?
Options
- ATransferring
- BEnhancing
- CSharing
- DExploiting
How the community answered
(48 responses)- A10% (5)
- B6% (3)
- C81% (39)
- D2% (1)
Community Discussion
No community discussion yet for this question.