The customer now needs the project's deliverable 3 months earlier than scheduled. The deliverable's quality has been reduced so the budget will not be impacted. Which of the following does the…

The correct answer is D. Schedule. See the full explanation below for the reasoning.

Question

The customer now needs the project's deliverable 3 months earlier than scheduled. The deliverable's quality has been reduced so the budget will not be impacted. Which of the following does the project manager need to update?

Options

  • AIssues Log
  • BCommunications Plan
  • CProject budget
  • DSchedule

How the community answered

(35 responses)
  • A
    3% (1)
  • B
    14% (5)
  • C
    9% (3)
  • D
    74% (26)